Pipe Filling AND Plugging- Place OUT OF Service (Item 0430830): FDOT Unit Price History
26 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure CY
- Weighted average (12 mo)
- $364.11/CY
- Contracts (12 mo)
- 26
- Total quantity (12 mo)
- 4,482.2 CY
- Total amount (12 mo)
- $1,631,999
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 18 | $471.61 | 1,375.62 | $648,753 |
| 2025 | 2025-01-01 – 2025-12-31 | 20 | $357.74 | 3,503.5 | $1,253,348 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 26 | $364.11 | 4,482.2 | $1,631,999 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $450.00 | +23.6% | 106.8 |
| 03 | 1 | $400.00 | +9.9% | 969.4 |
| 04 | 1 | $980.52 | +169.3% | 9 |
| 05 | 1 | $5,400.00 | +1,383.1% | 0.6 |
| 06 | 1 | $359.00 | -1.4% | 51.9 |
| 07 | 2 | $428.05 | +17.6% | 896.6 |
| 08 | 6 | $349.78 | -3.9% | 1,546.6 |
| 09 | 1 | $2,115.73 | +481.1% | 0.7 |
| 10 | 2 | $2,098.25 | +476.3% | 9.4 |
| 11 | 2 | $684.41 | +88% | 36.1 |
| 12 | 5 | $230.86 | -36.6% | 666 |
| 13 | 2 | $212.71 | -41.6% | 188.8 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0430830 (Pipe Filling AND Plugging- Place OUT OF Service) is measured in CY. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 26 contracts with a quantity-weighted average of $364.11 per CY, on 4,482.2 CY worth $1,631,999 in total.
The same report run for earlier periods shows $471.61 in 2024 (18 contracts, 1,375.62 CY), $357.74 in 2025 (20 contracts, 3,503.5 CY), $364.11 in the latest 12 months (26 contracts, 4,482.2 CY). From 2024 to the latest 12 months the weighted average fell 22.8%.
Quantity let statewide grew 226% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 12 of FDOT's 14 market areas reported this item: area 01 at $450.00 (1 contract), area 03 at $400.00 (1 contract), area 04 at $980.52 (1 contract), area 05 at $5,400.00 (1 contract), area 06 at $359.00 (1 contract), area 07 at $428.05 (2 contracts), area 08 at $349.78 (6 contracts), area 09 at $2,115.73 (1 contract), area 10 at $2,098.25 (2 contracts), area 11 at $684.41 (2 contracts), area 12 at $230.86 (5 contracts), area 13 at $212.71 (2 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.