Straight Concrete Endwalls, 18", Single, 0 Degrees, Round (Item 0430518100): FDOT Unit Price History
10 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $3,904.08/EA
- Contracts (12 mo)
- 10
- Total quantity (12 mo)
- 56 EA
- Total amount (12 mo)
- $218,629
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 13 | $4,888.33 | 30 | $146,650 |
| 2025 | 2025-01-01 – 2025-12-31 | 13 | $4,098.74 | 33 | $135,258 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 10 | $3,904.08 | 56 | $218,629 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 03 | 1 | $4,043.00 | +3.6% | 2 |
| 05 | 1 | $6,000.00 | +53.7% | 1 |
| 07 | 3 | $4,122.50 | +5.6% | 12 |
| 08 | 1 | $4,985.00 | +27.7% | 3 |
| 12 | 4 | $3,687.30 | -5.6% | 38 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0430518100 (Straight Concrete Endwalls, 18", Single, 0 Degrees, Round) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 10 contracts with a quantity-weighted average of $3,904.08 per EA, on 56 EA worth $218,629 in total.
The same report run for earlier periods shows $4,888.33 in 2024 (13 contracts, 30 EA), $4,098.74 in 2025 (13 contracts, 33 EA), $3,904.08 in the latest 12 months (10 contracts, 56 EA). From 2024 to the latest 12 months the weighted average fell 20.1%.
Quantity let statewide grew 87% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 5 of FDOT's 14 market areas reported this item: area 03 at $4,043.00 (1 contract), area 05 at $6,000.00 (1 contract), area 07 at $4,122.50 (3 contracts), area 08 at $4,985.00 (1 contract), area 12 at $3,687.30 (4 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.