Pipe Culvert,Optional Material,Other Shape-Elip/Arch, 24"S/CD (Item 0430175224): FDOT Unit Price History
11 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $202.21/LF
- Contracts (12 mo)
- 11
- Total quantity (12 mo)
- 3,184 LF
- Total amount (12 mo)
- $643,832
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 17 | $286.86 | 2,841 | $814,957 |
| 2025 | 2025-01-01 – 2025-12-31 | 16 | $200.14 | 3,545 | $709,484 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 11 | $202.21 | 3,184 | $643,832 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $179.00 | -11.5% | 298 |
| 03 | 1 | $203.10 | +0.4% | 532 |
| 05 | 1 | $805.00 | +298.1% | 8 |
| 07 | 1 | $154.00 | -23.8% | 1,336 |
| 08 | 4 | $267.36 | +32.2% | 483 |
| 09 | 1 | $350.00 | +73.1% | 78 |
| 10 | 1 | $360.00 | +78% | 17 |
| 12 | 1 | $249.31 | +23.3% | 432 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0430175224 (Pipe Culvert,Optional Material,Other Shape-Elip/Arch, 24"S/CD) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 11 contracts with a quantity-weighted average of $202.21 per LF, on 3,184 LF worth $643,832 in total.
The same report run for earlier periods shows $286.86 in 2024 (17 contracts, 2,841 LF), $200.14 in 2025 (16 contracts, 3,545 LF), $202.21 in the latest 12 months (11 contracts, 3,184 LF). From 2024 to the latest 12 months the weighted average fell 29.5%.
In the same 12 months, 8 of FDOT's 14 market areas reported this item: area 01 at $179.00 (1 contract), area 03 at $203.10 (1 contract), area 05 at $805.00 (1 contract), area 07 at $154.00 (1 contract), area 08 at $267.36 (4 contracts), area 09 at $350.00 (1 contract), area 10 at $360.00 (1 contract), area 12 at $249.31 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.