Pipe Culvert, OPT Material, Round, 54"S/CD (Item 0430175154): FDOT Unit Price History

11 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$524.21/LF
Contracts (12 mo)
11
Total quantity (12 mo)
8,840 LF
Total amount (12 mo)
$4,633,993

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-319$544.839,930$5,410,114
20252025-01-01 – 2025-12-3112$483.737,079$3,424,310
Latest 12 months2025-11-01 – 2026-10-3111$524.218,840$4,633,993

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
011$425.00-18.9%53
061$393.10-25%2,871
073$333.79-36.3%2,455
081$994.46+89.7%16
102$1,029.77+96.4%69
122$774.86+47.8%48
131$763.00+45.6%3,328

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0430175154 (Pipe Culvert, OPT Material, Round, 54"S/CD) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 11 contracts with a quantity-weighted average of $524.21 per LF, on 8,840 LF worth $4,633,993 in total.

The same report run for earlier periods shows $544.83 in 2024 (9 contracts, 9,930 LF), $483.73 in 2025 (12 contracts, 7,079 LF), $524.21 in the latest 12 months (11 contracts, 8,840 LF). From 2024 to the latest 12 months the weighted average fell 3.8%.

In the same 12 months, 7 of FDOT's 14 market areas reported this item: area 01 at $425.00 (1 contract), area 06 at $393.10 (1 contract), area 07 at $333.79 (3 contracts), area 08 at $994.46 (1 contract), area 10 at $1,029.77 (2 contracts), area 12 at $774.86 (2 contracts), area 13 at $763.00 (1 contract).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.