Pipe Culvert, OPT Material, Round, 30"S/CD (Item 0430175130): FDOT Unit Price History

33 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$228.86/LF
Contracts (12 mo)
33
Total quantity (12 mo)
36,496 LF
Total amount (12 mo)
$8,352,394

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3145$227.2533,712$7,660,988
20252025-01-01 – 2025-12-3144$197.5950,436$9,965,527
Latest 12 months2025-11-01 – 2026-10-3133$228.8636,496$8,352,394

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
011$142.00-38%3,491
021$660.20+188.5%32
031$123.55-46%3,329
053$330.77+44.5%941
063$192.70-15.8%1,721
074$157.06-31.4%14,783
088$191.72-16.2%5,612
091$565.12+146.9%64
105$376.59+64.6%1,090
125$186.84-18.4%4,366
131$1,988.00+768.7%1,067

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0430175130 (Pipe Culvert, OPT Material, Round, 30"S/CD) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 33 contracts with a quantity-weighted average of $228.86 per LF, on 36,496 LF worth $8,352,394 in total.

The same report run for earlier periods shows $227.25 in 2024 (45 contracts, 33,712 LF), $197.59 in 2025 (44 contracts, 50,436 LF), $228.86 in the latest 12 months (33 contracts, 36,496 LF). Across those periods the weighted average stayed within three percent.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 6 market areas with at least three contracts, market area 07 had the lowest weighted average ($157.06 per LF, 4 contracts) and market area 10 the highest ($376.59, 5 contracts), 2.4 times as much. Market area 08 let the most contracts with this item (8). 11 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.