Pipe Culvert, Optional Material, Other Shape - Ellip/Arch, 18"SD (Item 0430174218): FDOT Unit Price History

17 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$154.57/LF
Contracts (12 mo)
17
Total quantity (12 mo)
3,266 LF
Total amount (12 mo)
$504,823

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3129$229.915,017$1,153,482
20252025-01-01 – 2025-12-3118$200.372,231$447,029
Latest 12 months2025-11-01 – 2026-10-3117$154.573,266$504,823

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
011$161.00+4.2%450
021$122.39-20.8%56
032$235.13+52.1%83
041$201.35+30.3%144
061$239.21+54.8%35
077$131.14-15.2%2,019
092$280.83+81.7%156
131$250.00+61.7%143

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0430174218 (Pipe Culvert, Optional Material, Other Shape - Ellip/Arch, 18"SD) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 17 contracts with a quantity-weighted average of $154.57 per LF, on 3,266 LF worth $504,823 in total.

The same report run for earlier periods shows $229.91 in 2024 (29 contracts, 5,017 LF), $200.37 in 2025 (18 contracts, 2,231 LF), $154.57 in the latest 12 months (17 contracts, 3,266 LF). From 2024 to the latest 12 months the weighted average fell 32.8%.

Quantity let statewide shrank 35% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

In the same 12 months, 8 of FDOT's 14 market areas reported this item: area 01 at $161.00 (1 contract), area 02 at $122.39 (1 contract), area 03 at $235.13 (2 contracts), area 04 at $201.35 (1 contract), area 06 at $239.21 (1 contract), area 07 at $131.14 (7 contracts), area 09 at $280.83 (2 contracts), area 13 at $250.00 (1 contract).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.