Pipe Culvert, Optional Material, Other Shape - Ellip/Arch, 18"SD (Item 0430174218): FDOT Unit Price History
17 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $154.57/LF
- Contracts (12 mo)
- 17
- Total quantity (12 mo)
- 3,266 LF
- Total amount (12 mo)
- $504,823
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 29 | $229.91 | 5,017 | $1,153,482 |
| 2025 | 2025-01-01 – 2025-12-31 | 18 | $200.37 | 2,231 | $447,029 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 17 | $154.57 | 3,266 | $504,823 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $161.00 | +4.2% | 450 |
| 02 | 1 | $122.39 | -20.8% | 56 |
| 03 | 2 | $235.13 | +52.1% | 83 |
| 04 | 1 | $201.35 | +30.3% | 144 |
| 06 | 1 | $239.21 | +54.8% | 35 |
| 07 | 7 | $131.14 | -15.2% | 2,019 |
| 09 | 2 | $280.83 | +81.7% | 156 |
| 13 | 1 | $250.00 | +61.7% | 143 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0430174218 (Pipe Culvert, Optional Material, Other Shape - Ellip/Arch, 18"SD) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 17 contracts with a quantity-weighted average of $154.57 per LF, on 3,266 LF worth $504,823 in total.
The same report run for earlier periods shows $229.91 in 2024 (29 contracts, 5,017 LF), $200.37 in 2025 (18 contracts, 2,231 LF), $154.57 in the latest 12 months (17 contracts, 3,266 LF). From 2024 to the latest 12 months the weighted average fell 32.8%.
Quantity let statewide shrank 35% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 8 of FDOT's 14 market areas reported this item: area 01 at $161.00 (1 contract), area 02 at $122.39 (1 contract), area 03 at $235.13 (2 contracts), area 04 at $201.35 (1 contract), area 06 at $239.21 (1 contract), area 07 at $131.14 (7 contracts), area 09 at $280.83 (2 contracts), area 13 at $250.00 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.