Pipe Culvert, Optional Material, Round, 24"SD (Item 0430174124): FDOT Unit Price History
12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $129.99/LF
- Contracts (12 mo)
- 12
- Total quantity (12 mo)
- 1,992 LF
- Total amount (12 mo)
- $258,938
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 27 | $188.35 | 2,874 | $541,304 |
| 2025 | 2025-01-01 – 2025-12-31 | 18 | $239.38 | 5,198 | $1,244,293 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 12 | $129.99 | 1,992 | $258,938 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $178.00 | +36.9% | 290 |
| 02 | 2 | $111.23 | -14.4% | 203 |
| 03 | 1 | $122.26 | -5.9% | 62 |
| 07 | 6 | $119.86 | -7.8% | 913 |
| 08 | 1 | $155.57 | +19.7% | 138 |
| 12 | 1 | $119.84 | -7.8% | 386 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0430174124 (Pipe Culvert, Optional Material, Round, 24"SD) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $129.99 per LF, on 1,992 LF worth $258,938 in total.
The same report run for earlier periods shows $188.35 in 2024 (27 contracts, 2,874 LF), $239.38 in 2025 (18 contracts, 5,198 LF), $129.99 in the latest 12 months (12 contracts, 1,992 LF). From 2024 to the latest 12 months the weighted average fell 31.0%.
Quantity let statewide shrank 31% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 6 of FDOT's 14 market areas reported this item: area 01 at $178.00 (1 contract), area 02 at $111.23 (2 contracts), area 03 at $122.26 (1 contract), area 07 at $119.86 (6 contracts), area 08 at $155.57 (1 contract), area 12 at $119.84 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.