Composite Neoprene Pads (Item 0400147): FDOT Unit Price History

15 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure CF

Weighted average (12 mo)
$1,601.57/CF
Contracts (12 mo)
15
Total quantity (12 mo)
634.8 CF
Total amount (12 mo)
$1,016,679

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-319$1,276.43417.4$532,783
20252025-01-01 – 2025-12-3123$1,321.971,043.6$1,379,606
Latest 12 months2025-11-01 – 2026-10-3115$1,601.57634.8$1,016,679

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
021$1,500.00-6.3%9.6
031$2,300.00+43.6%18.6
041$1,700.00+6.1%17.9
074$1,262.76-21.2%203.3
082$2,172.65+35.7%16.4
101$1,400.00-12.6%131.4
111$1,690.00+5.5%78
124$2,010.89+25.6%159.6

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0400147 (Composite Neoprene Pads) is measured in CF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 15 contracts with a quantity-weighted average of $1,601.57 per CF, on 634.8 CF worth $1,016,679 in total.

The same report run for earlier periods shows $1,276.43 in 2024 (9 contracts, 417.4 CF), $1,321.97 in 2025 (23 contracts, 1,043.6 CF), $1,601.57 in the latest 12 months (15 contracts, 634.8 CF). From 2024 to the latest 12 months the weighted average rose 25.5%.

Quantity let statewide grew 52% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

In the same 12 months, 8 of FDOT's 14 market areas reported this item: area 02 at $1,500.00 (1 contract), area 03 at $2,300.00 (1 contract), area 04 at $1,700.00 (1 contract), area 07 at $1,262.76 (4 contracts), area 08 at $2,172.65 (2 contracts), area 10 at $1,400.00 (1 contract), area 11 at $1,690.00 (1 contract), area 12 at $2,010.89 (4 contracts).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.