Asphalt Concrete Friction Course,Traffic C, FC-9.5, PG 76-22 (Item 0337 7 82): FDOT Unit Price History
18 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure TN
- Weighted average (12 mo)
- $165.96/TN
- Contracts (12 mo)
- 18
- Total quantity (12 mo)
- 96,263.4 TN
- Total amount (12 mo)
- $15,975,445
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 36 | $195.63 | 136,037.4 | $26,612,418 |
| 2025 | 2025-01-01 – 2025-12-31 | 25 | $204.77 | 65,230.1 | $13,357,227 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 18 | $165.96 | 96,263.4 | $15,975,445 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 2 | $147.30 | -11.2% | 27,791.6 |
| 03 | 1 | $153.00 | -7.8% | 11,143.4 |
| 05 | 1 | $124.42 | -25% | 11,608.8 |
| 06 | 1 | $135.23 | -18.5% | 1,737.5 |
| 08 | 2 | $225.82 | +36.1% | 9,829.4 |
| 10 | 1 | $160.00 | -3.6% | 9,534.2 |
| 11 | 1 | $165.00 | -0.6% | 12,043.2 |
| 12 | 4 | $213.00 | +28.3% | 4,309 |
| 13 | 5 | $223.50 | +34.7% | 8,266.3 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0337 7 82 (Asphalt Concrete Friction Course,Traffic C, FC-9.5, PG 76-22) is measured in TN. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 18 contracts with a quantity-weighted average of $165.96 per TN, on 96,263.4 TN worth $15,975,445 in total.
The same report run for earlier periods shows $195.63 in 2024 (36 contracts, 136,037.4 TN), $204.77 in 2025 (25 contracts, 65,230.1 TN), $165.96 in the latest 12 months (18 contracts, 96,263.4 TN). From 2024 to the latest 12 months the weighted average fell 15.2%.
Quantity let statewide shrank 29% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 9 of FDOT's 14 market areas reported this item: area 01 at $147.30 (2 contracts), area 03 at $153.00 (1 contract), area 05 at $124.42 (1 contract), area 06 at $135.23 (1 contract), area 08 at $225.82 (2 contracts), area 10 at $160.00 (1 contract), area 11 at $165.00 (1 contract), area 12 at $213.00 (4 contracts), area 13 at $223.50 (5 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0337: 0337 7 83 Asphalt Concrete Friction Course,Traffic C, FC-12.5, PG 76-22 ($160.59 per TN, 129 contracts); 0337 7 25 Asphalt Concrete Friction Course, INC BIT, FC-5, PG 76-22 ($202.39 per TN, 54 contracts); 0337 7 81 Asphalt Concrete Friction Course,Traffic B, FC-12.5, PG 76-22 ($150.74 per TN, 48 contracts); 0337 7 88 Asphalt Concrete Friction Course,Traffic E, FC-12.5, PG 76-22 ($171.07 per TN, 20 contracts); 0337 7 26 Asphalt Concrete Friction Course, INC BIT, FC-5, High Polymer ($211.79 per TN, 4 contracts).
Related items in section 0337
- 0337 7 83 · Asphalt Concrete Friction Course,Traffic C, FC-12.5, PG 76-22 ($160.59/TN)
- 0337 7 25 · Asphalt Concrete Friction Course, INC BIT, FC-5, PG 76-22 ($202.39/TN)
- 0337 7 81 · Asphalt Concrete Friction Course,Traffic B, FC-12.5, PG 76-22 ($150.74/TN)
- 0337 7 88 · Asphalt Concrete Friction Course,Traffic E, FC-12.5, PG 76-22 ($171.07/TN)
- 0337 7 26 · Asphalt Concrete Friction Course, INC BIT, FC-5, High Polymer ($211.79/TN)
- 0337 7 80 · Asphalt Concrete Friction Course,Traffic B, FC-9.5, PG 76-22 ($200.09/TN)
- 0337 7 93 · Asphalt Concrete Friction Course,Traffic C, FC-12.5, High Polymer ($172.45/TN)
- 0337 7 95 · Asphalt Concrete Friction Course,Traffic E, FC-12.5, High Polymer ($304.88/TN)