Optional Base, Base Group 03 (Item 0285703): FDOT Unit Price History
15 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure SY
- Weighted average (12 mo)
- $19.78/SY
- Contracts (12 mo)
- 15
- Total quantity (12 mo)
- 104,368 SY
- Total amount (12 mo)
- $2,064,528
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 15 | $11.73 | 113,675 | $1,333,330 |
| 2025 | 2025-01-01 – 2025-12-31 | 15 | $21.16 | 70,052 | $1,482,363 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 15 | $19.78 | 104,368 | $2,064,528 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $24.00 | +21.3% | 3,617 |
| 02 | 1 | $32.00 | +61.8% | 361 |
| 03 | 2 | $49.90 | +152.3% | 933 |
| 04 | 2 | $45.87 | +131.9% | 2,083 |
| 05 | 1 | $96.79 | +389.3% | 170 |
| 07 | 3 | $17.54 | -11.3% | 14,497 |
| 09 | 1 | $49.58 | +150.7% | 951 |
| 10 | 2 | $129.31 | +553.7% | 80 |
| 12 | 2 | $18.31 | -7.4% | 81,676 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0285703 (Optional Base, Base Group 03) is measured in SY. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 15 contracts with a quantity-weighted average of $19.78 per SY, on 104,368 SY worth $2,064,528 in total.
The same report run for earlier periods shows $11.73 in 2024 (15 contracts, 113,675 SY), $21.16 in 2025 (15 contracts, 70,052 SY), $19.78 in the latest 12 months (15 contracts, 104,368 SY). From 2024 to the latest 12 months the weighted average rose 68.6%.
In the same 12 months, 9 of FDOT's 14 market areas reported this item: area 01 at $24.00 (1 contract), area 02 at $32.00 (1 contract), area 03 at $49.90 (2 contracts), area 04 at $45.87 (2 contracts), area 05 at $96.79 (1 contract), area 07 at $17.54 (3 contracts), area 09 at $49.58 (1 contract), area 10 at $129.31 (2 contracts), area 12 at $18.31 (2 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.