Temporary Signalization AND Maintenance, Intersection (Item 0102104): FDOT Unit Price History
143 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure ED
- Weighted average (12 mo)
- $18.47/ED
- Contracts (12 mo)
- 143
- Total quantity (12 mo)
- 216,036 ED
- Total amount (12 mo)
- $3,989,862
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 187 | $26.48 | 277,438 | $7,346,670 |
| 2025 | 2025-01-01 – 2025-12-31 | 176 | $23.76 | 258,997 | $6,154,887 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 143 | $18.47 | 216,036 | $3,989,862 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 6 | $11.26 | -39% | 22,465 |
| 02 | 4 | $14.68 | -20.5% | 1,350 |
| 03 | 7 | $14.76 | -20.1% | 9,508 |
| 04 | 5 | $37.75 | +104.4% | 5,620 |
| 05 | 12 | $25.23 | +36.6% | 12,330 |
| 06 | 12 | $27.51 | +48.9% | 17,725 |
| 07 | 17 | $18.51 | +0.2% | 15,604 |
| 08 | 34 | $18.47 | 0% | 61,559 |
| 09 | 3 | $8.07 | -56.3% | 6,525 |
| 10 | 11 | $35.57 | +92.6% | 10,435 |
| 11 | 4 | $8.32 | -55% | 4,495 |
| 12 | 18 | $15.85 | -14.2% | 20,202 |
| 13 | 10 | $12.71 | -31.2% | 28,218 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0102104 (Temporary Signalization AND Maintenance, Intersection) is measured in ED. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 143 contracts with a quantity-weighted average of $18.47 per ED, on 216,036 ED worth $3,989,862 in total.
The same report run for earlier periods shows $26.48 in 2024 (187 contracts, 277,438 ED), $23.76 in 2025 (176 contracts, 258,997 ED), $18.47 in the latest 12 months (143 contracts, 216,036 ED). From 2024 to the latest 12 months the weighted average fell 30.2%.
Quantity let statewide shrank 22% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 13 market areas with at least three contracts, market area 09 had the lowest weighted average ($8.07 per ED, 3 contracts) and market area 04 the highest ($37.75, 5 contracts), 4.7 times as much. Market area 08 let the most contracts with this item (34). 13 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.