Texas Lime Company: TxDOT Bid Results and Margins

Name as published by TxDOT: TEXAS LIME COMPANY · Data as published by TxDOT, lettings Mar 24, 2025 to Aug 12, 2026, retrieved Nov 24, 2026.

Proposals bid
8
Low bids (rank 1)
8
Win rate
100%
Low-bid value
$302K
Money left on table
$78K
Avg. bid vs. estimate
+4.77%

From Mar 24, 2025 to Aug 12, 2026, Texas Lime Company submitted 8 bids on TxDOT proposals and was the apparent low bidder on 8 of them (100%), with low bids totalling $301,538. In 7 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $78,400 (27.71% of those bids); the median gap was 24.14%. On average its bids came in 4.77% above TxDOT's engineer's estimate. Its most frequent district was Yoakum (5 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
202533100.0%$88,350
202655100.0%$213,188

Head-to-head rivals

BidderProposals togetherRanked ahead
Touchstone Resources, LLC77 of 7

Districts and work types

DistrictBids
Yoakum5
Amarillo2
Dallas1
Work type of low bidsLow bids
Material Maintenance Project8

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-08-126500-48-001KaufmanMaterial Maintenance Project1 of 2$14,500—+24.7%
2026-04-226495-89-001VictoriaMaterial Maintenance Project1 of 2$20,475—+4%
2026-04-226498-79-001RandallMaterial Maintenance Project1 of 2$48,600—+9.3%
2026-03-246494-65-001FayetteMaterial Maintenance Project1 of 2$25,725—-2%
2026-02-176494-38-001WhartonMaterial Maintenance Project1 of 2$103,888—+7.9%
2025-04-236482-27-001RandallMaterial Maintenance Project1 of 2$44,460—-1.2%
2025-04-216477-06-001VictoriaMaterial Maintenance Project1 of 1$18,638—+2.9%
2025-03-246476-80-001FayetteMaterial Maintenance Project1 of 2$25,253—-7.5%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.