Overland Materials & Manufacturing, Inc.: TxDOT Bid Results and Margins

Name as published by TxDOT: OVERLAND MATERIALS & MANUFACTURING, INC. · Data as published by TxDOT, lettings Feb 26, 2025 to Aug 20, 2026, retrieved Nov 24, 2026.

Proposals bid
14
Low bids (rank 1)
9
Win rate
64.29%
Low-bid value
$5.9M
Money left on table
$268K
Avg. bid vs. estimate
-0.31%

From Feb 26, 2025 to Aug 20, 2026, Overland Materials & Manufacturing, Inc. submitted 14 bids on TxDOT proposals and was the apparent low bidder on 9 of them (64.29%), with low bids totalling $5,887,735. In 8 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $268,366 (5.4% of those bids); the median gap was 3.87%. On average its bids came in 0.31% below TxDOT's engineer's estimate. Its most frequent district was Wichita Falls (10 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
20257685.7%$3,830,703
20267342.9%$2,057,032

Head-to-head rivals

BidderProposals togetherRanked ahead
Jagoe-Public Company97 of 9
Eurovia Atlantic Coast LLC75 of 7
Austin Asphalt, Inc.53 of 5
Zack Burkett Co.55 of 5
Rk Hall, LLC30 of 3
Southern Sourcing Solutions, LLC33 of 3
Reynolds Asphalt & Construction Company22 of 2
Touchstone Resources, LLC22 of 2

Districts and work types

DistrictBids
Wichita Falls10
Paris4
Work type of low bidsLow bids
Material Maintenance Project8
Material Maintenance Project - Sealed1

Closest second-place finishes

Let dateProposalCountyLow bidderLow bidThis bidvs. low bid
2025-04-176478-48-001FanninRk Hall, LLC$747,200$749,900+0.4%
2026-08-206506-71-001GraysonRk Hall, LLC$596,250$728,875+22.2%

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-08-206506-71-001GraysonMaterial Maintenance Project - Sealed2 of 4$728,875+22.2%+4.1%
2026-06-176502-23-001MontagueMaterial Maintenance Project4 of 5$665,156+4.2%+7.5%
2026-06-176502-24-001CookeMaterial Maintenance Project1 of 5$578,755—-6.5%
2026-06-176502-26-001ClayMaterial Maintenance Project4 of 5$672,319+5.1%+8.6%
2026-06-176502-28-001WilbargerMaterial Maintenance Project1 of 2$764,811—+23.6%
2026-06-176502-29-001WichitaMaterial Maintenance Project1 of 3$713,466—-9.8%
2026-04-166499-97-001FanninMaterial Maintenance Project - Sealed3 of 5$863,500+23.8%+15.6%
2025-08-216487-94-001GraysonMaterial Maintenance Project - Sealed1 of 1$913,875—+7.1%
2025-04-176478-48-001FanninMaterial Maintenance Project - Sealed2 of 3$749,900+0.4%-1.6%
2025-02-266476-43-001ClayMaterial Maintenance Project1 of 4$589,235—-8.1%
2025-02-266476-44-001CookeMaterial Maintenance Project1 of 4$539,206—-14.2%
2025-02-266476-45-001MontagueMaterial Maintenance Project1 of 4$556,528—-12.3%